Dear All

I have created order for 01.11.2008 on 18.11.2008.Changed the document date,Delivery date to 01.11.2008.Good Reciept was already done for 01.11.2008 but when i run Availibility check it confirms the material on current date only.I need to deliver the material on backdate.Availibirity check on material master is "Individual requirement".please suggest what should i do?

Thanks in Advance

Nomi

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

hello, friend.

i believe the system processes deliveries and scheduling (including shipments, staging, picking, etc.) in real time. ergo, availability check uses real time. nevertheless, maybe somebody can offer a contrary opinion on this issue.

however, if you want to reflect postings in the past, you may consider using the 'actual PGI date' in the delivery document instead.