on 11-18-2008 5:11 AM
Hi ALL,
T/Code u2013 S_ALR_87013558
Executing this report against WBS, and it is showing u2013ve value against one of the WBS, when I drill down it shows 3 WBS & 1 maintenance order (in the end) comes up showing negative value in commitment column.
But when I check Maintenance Order Budget commitment report in IW32 it shows ZERO against commitment.
There is a PR against this order which further has lot of POu2019s n GRNu2019s, but not able to figure out the reason for NEGATIVE COMMITMENT VALUE??
Can anyone guide something on this?
THANKS
DM
Hi,
I also got this issue, it seems when u delete line items on PO/PR, this issue might come but once i execute CJEN it was sorted out, so just try CJEN
Reg,
Sam
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Evaluating Commitments in the Cost Element Report By T-code GR55.
Regards
Prathamesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
96 | |
10 | |
9 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.