I got a problem here,

I have created a project. I have attached material also. I have a specific requirment. I want to creat bill of material for the material I have attached. I want to create different requisitions for all the child items. Is it possible? If yes, How?

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

hi,

after you create BOM using CS01, you explode the BOM in the project (Edit -- Component -- Explode BOM)..

or, you can define reference points in SPRO, then set the reference point in BOM and activity then execute BOM transfer function using CN33

goodluck..

Former Member
0 Kudos

Thank you very much for the reply.

However, please note the field "Explode BOM" is not enabled. It is a grey field. I think I will have to contact administrator and get this enabled. Is it right? or there can be any other reason?

Please help.

Hemant Ghodke

Former Member
0 Kudos

hi..

in cj20n, click on an activity then click on component overview..

than go to edit -- component -- explode bom..

should be activated.. (must be in component overview to be able to explode bom)

pls try..

Former Member
0 Kudos

Thank you Mr. Ramesh & Mr. Virendra Pal,

It is working now.

Regards,

Hemant

Former Member
0 Kudos

i think its best to thank other users by awarding points..

cheers..

Emman

Answers (1)

Answers (1)

virendra_pal
Active Contributor
0 Kudos

use CS01 to create a material BOM

in your neetwork parameter config OPUV do not tick collective requisition