on 11-17-2008 11:30 AM
Dear PS Experts,
Our client wants to implement IM with IO's for individual assets.and also need to implement PS for Land or Bulding as a projects.
Can we go for both Internal order and WBS as investment measures with IM. how it is possible?
Thanks,
Sanju.
It is very much possible.
Refer below link....
http://help.sap.com/saphelp_470/helpdata/en/2a/f9fefd493111d182b70000e829fbfe/frameset.htm
Make sure that Investment program type allows WBS and Internal order as measures.
SPRO->Investment Management->Investment Programs->Master Data->Define Program Types
Venkat
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
I would recommend to use only one process for IM i.e. use only one object which canbe used for both your requirements
WBS is the answer
use WBS statistically for direct asset purchase via MM (laptop)
and use WBS proper for land and building
by using only one cost object as investment measure you will save implementation cost as system needs to be set up for WBS only, less training costs and consistent approach across your business
you can now use the inv program and use the same budget for laptop and land etc
Possible. While creating Investment program type...assign orders and Projects as a operative object types.
Regards
Hemant
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.