hi,
while doing confirmation in ( SRM 4.0 ), the qty ordered is showing wrong value .
what could be reason for this ..
any clues...
venga
this is happend to only 1 SC . later we found correct qty for the same SC .
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Are you mean PO quantity wrong? check version tab in your PO .
regards
Muthu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
It is strange and wrong.As per standard it must copy the same data to the follow on document in PO. You are stating that R/3 PO ordered quantity is same as equivalent to SC but ECS PO ordered quantity is not matching with SC ordered quantity. Are you geting for only one po like this ? are disprecencies happen for all pos?