Dear All,
I have scenario as client requirement is that they want to do Die maitenance on time based & performance .For performance base they want to update the counter value from production product value ( Finish good product +Rejected goods product) .
I created Die as equipment with fill data in PRT tab measuring point & maintenance plan .
So what is procedure to update these measuring counter from prodction order.
Pl help in these scenario.
Avi
hi
kindly refer [Performance-based Completion Confirmations from Production|http://help.sap.com/saphelp_46c/helpdata/en/fe/67ef189d6f11d189b60000e829fbbd/content.htm]
regards
thyagarajan