Error coming while creating sales order Thru' Assembly processing.u00A0

Former Member
0 Kudos

Hi,

I am working on assembly processing. when i am creating sales order if order qty when i am giving more then 999 means if i given 1000 kg it giving an error like the exection factor in the network is reduced to 1000 to 1 kg and confimed as 1 kg only and system is giving msg *Change not accepted (execution factor in network too large)* where i have tomodify this .

In above context i would like to brief you that i can't extend quantity more then 999(Three alfabet).

All suggestions will be apreciated with good points.

Regards,

Vishal Kr. Sharma

Accepted Solutions (1)

Accepted Solutions (1)

former_member217082
Active Contributor
0 Kudos

Hi vishal

Check in MMR the following settings :

1) Base unit of measure

2) sales unit

3) Strategy group maintained in MMR ->MRP 3 view

4) Availability check(sales/general plant view in MMR ) and MRP type (MRP1 view in MMR) has been maintained or not.

5) Check the fields maintained in the MRP 3 view.

Regards

Srinath

Former Member
0 Kudos

Hi,

Thanx for your reply.

I have already maintain these things in material master because there is no problem while creating SO if qty. is less than 999. but if i am taking qty. as more than 999 then system is throwing error as earlier post.

Regards,

Vishal Kr. Sharma

Answers (1)

Answers (1)

Lakshmipathi
Active Contributor
0 Kudos

Dear Vishal

Check in material master Basic Data1 what UoM is maintained there. Is it grams or kgs ??

thanks

G. Lakshmipathi

Former Member
0 Kudos

Hi lakshi,

I have check it's.

it is KG.

Regards,

Vishal Kr. Sharma