on 11-14-2008 10:19 AM
Dear Gurus,
My scenario is like this...
I have a project made in plant A (profile belongs to plant A).
I have added the trading material available in plant B into my project.
I want to do project delivery from plant B.
When I run the transaction cns0, I could not able to saw that material.
Can anyone suggest me.....what would be the problem??
Also tell me fundamentally can I do this kind of scenario through project.
Thanks in advance for replies.
Best Regards,
Parimal.
U should create an activity with Plant B in the project and attache material. Then create delivery.
Hope both the plants belongs to same comany code.
Venkat
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.