Dear experts,

Kindly suggent me for the below scenario...

My client wants to procure the goods from the project stock. The goods must be issued from the Project stock.

I am creating sales order and assigning the WBS element in the account assignment key.. i wann know that how should i deliver the goods from the project stock,,,, wat is the configurations needs to be done.

i had checked in requirement class.. ther i could not find any Delivery with project stock.. where in Schedule lines there is LP : Dlv. from project. in this shedule line there is no Movement type nuthin.. could anyone suggest me how to deliver the goods from the project stock.

Regards

abhi

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Done...

Former Member
0 Kudos

Dear Experts,

Anyone in this taks....

Have any doubts kindly let me know

Former Member
0 Kudos

Hi

You can try 221 movement type which is goods issue for a project.

Regards

Subhasish