With a multi capacity resource, how can I set up a ppm so that I can view capacity utilization at individual capacity level in PPT(PPDS)?
Any inputs are welcome
Vard
Suggest using "Modes" in PPM. Mode 01 will have "x" capacity, mode 02 will have "y" capacity and so on. You will have to give a slightly different resource name for each mode. E.g, If there is a multi capacity resource named "RESOURCE", then first create following resources in the Resource master : RESOURCE_X and RESOURCE_Y. Define individual capacities ( Resource is same, only we are separating capacities). Then include these in the PPM - mode 01 = RESOURCE_X, mode 02 = RESOURCE_Y.
Hoe this helps