How to configure PPM for individual capacities of a resource

Former Member
0 Kudos

With a multi capacity resource, how can I set up a ppm so that I can view capacity utilization at individual capacity level in PPT(PPDS)?

Any inputs are welcome

Vard

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Suggest using "Modes" in PPM. Mode 01 will have "x" capacity, mode 02 will have "y" capacity and so on. You will have to give a slightly different resource name for each mode. E.g, If there is a multi capacity resource named "RESOURCE", then first create following resources in the Resource master : RESOURCE_X and RESOURCE_Y. Define individual capacities ( Resource is same, only we are separating capacities). Then include these in the PPM - mode 01 = RESOURCE_X, mode 02 = RESOURCE_Y.

Hoe this helps