Hi experts
pls explain me the diff between Material BOM & WBS BOM??
Thanks
Tanveer
Hi
WBS BOMs are mainly used together with production lots. They are bills of material that are valid only for a particular WBS element. That means it is project/WBS sepecific and can not be used by other project/WBS.
While Material BOM is generic. Please refer
http://help.sap.com/saphelp_47x200/helpdata/en/ea/e9b0724c7211d189520000e829fbbd/content.htm