Hi PS Experts,
My Project have WBS then Network and activities.
Since my top level WBS is billing element , have to release the WBS for billing purpose.
But need to restrict the REL of activities under the same WBS..So that I have to restrict confirmations etc.
The project is phase by phase so some activities should be restricted for actual confirmations etc..
Any help with user status?
thnx in advance.
psconsultant
tx OK02
create a user status profile
create a user status to be set on release with restrcition of what you do not need
add the user status profile to the project profile
note - if you have not used user status profile before then the change will not be retrospective
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Virendra/Pushpa,
Thanks for the response. I did try the user status . In this case I have to select lot of radio buttons which should not allow at for this user status..
What I am trying to achive is to deactivate the activity REL with WBS REL, so that user should not able to do transaction ( confirmation,actual postings ...) which are possible with REL status.
I could still do that with user status which doesn't allow REL of activity.
But when I RELEASE WBS, system trying to release the activity also and unable to release the activity because of my user staus..
Edited by: psconsultant on Nov 12, 2008 9:51 PM
Edited by: psconsultant on Nov 12, 2008 9:52 PM
create user status ZREL
disallow all the business transactions that you want - you have to selkect all the radio buttons like confirmations, i posting setc
in the business transaction Release choose the set radio button
this will set the user status ZREL when you REL WBS and disallow the business transactions as configured
Hi Virendra,
Thanks again.. As I mentioned we have the billing WBS at level 1 and then level 2 WBS elements. All activities are under level 2 WBS. All level 2 WBS are phase wise.
Part of our business process Level 1 WBS to be released for billing , but need to restrict the activities under level 2 WBS for actual.
I already done the config. you had mentioned. This way we can put the user status at activity level upon Level 1 REL, but user have to go to each activity and change the user status to make confirmations or actual postings etc. thatu2019s a pain.
What I did is control the actuals at activity level by putting lock account assignment status. The same pain here is to go to each activity and change the user status to make confirmations etc..
hi ,
cerate a user stastus for networks ... PHS1 which gets activiated with release or created stage and in this user status you can forbid confirmations and another user status PHS2 which can be changed by an authorised person thru authrosation key and in this you can allow confirmations .... kindly check
regrds
pushpa
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
97 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.