on 11-12-2008 3:50 AM
Hi,
My requirement is ,
customer ordered X,Y,Z material each material order quantity is 25 ,,,means
X-25
y-25
z-25...
but i need to delivery x-10
y-10
z-10 on 12.11.08 at a time
and x-15
y-15
z-15 on 1.12.08.......How can i frame it into SAP.
Plzz revert me back if you need more clarity
Regards
Raj
Dear Venky,
Through Scheduling agreement process your requirement will get full filled.
Go to VA31 transaction
Enter scheduling agreement type
Enter sales area
Press enter now system will take you to the Create sceduling agreement over view screen here you enter customer and material (X-25y,-25,z-25..)then select the line item go to menu >Goto>item-->Schedule lines here you enter the data
X-10
y-10
z-10 delivery date on 12.11.08
X-15
y-15
z-15...delivery date on 1.12.08 save the scheduling agreement, now you can create deliveries in those respective dates (12.11.08 and 1.12.08).
I hope this will help you,
Regards,
Murali.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.