Equivalent parameter for 'Avoid Surpluses' in SNP for heuristics

Former Member
0 Kudos

Hello Gurus,

In PPDS heuristics profile we have a parameter called PROCEDURE Where we have the options like 'Avoid Surpluses', 'FIFO' and 'Avoid Delays'. Please let me know what is equivalent parameters for this in SNP heuristics. I want the same functionality to be activated in SNP ( Mainly for the option ''Avoid Surpluses" ).

Thanks,

Siva.

Accepted Solutions (1)

Accepted Solutions (1)

nitin_thatte
Contributor
0 Kudos

Hi Siva

There is no setting in SNP which is equivalent to avoid surplus.

However I do not see any reason why SNP heuristic would plan excess production except "fixed lot size" and "Rounding Value". This setting is not necessary in SNP.

Could you elaborate more abut your problem?

Regards,

Nitin Thatte

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Siva,

could you please let me know what is your observation when executing the SNP heuristcs ?

does it create surplus receipts..? and what is the lot size defined for the products ?

cheers

Ram