How to schedule the Early Watch Report

yogesh_galphade
Contributor
0 Kudos

Hi

I want to schedule the Early watch report job. Now I am doing it manually by downloading the xml data(from Portal ) and uploading in solman to get the report.

Please tell me the procedure.

Thanks in advance

Yogesh

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Yogesh,

Probably you should check note 738676 and the attachment to it.

best regards,

-David.

yogesh_galphade
Contributor
0 Kudos

Hi David

Thanks for your immediate reply. But I need the exact procedure to scheduling the job for portal EWR.

Former Member
0 Kudos

Hi Yogesh,

Check out 'Note 976054 - Availability of EWA for Non ABAP components'.

The attachment in the note provides the steps for achieving the same. Check out the section 2.3.1.

Kind Regards,

Mrityunjay.