Activity missing in Workforce planning:project view

Former Member
0 Kudos

Dear experts,

I an caught up with the following problem:

1) I created a project with WBS and activities.

2) Created relationship between activities.

3) Created project team

When I try to perform workforce planning (project view) using transaction CMP2, some of the activities are missing in the list.

Please let me why this happens and also how to include the missing activities.

Thanks and regards

Accepted Solutions (0)

Answers (4)

Answers (4)

virendra_pal
Active Contributor
0 Kudos

open project in Project planning board

go to Edit -> function -> activate capacities

then Go to -> capacity levelling -> workforce planning

if this does not work then check the configuration/ details as explained by Hemant

Former Member
0 Kudos

The problem would be workcenters. Check whether you have assigned it in the activity. Along with workcenter provide allocated hours and a distribution rule. Check and confirm.

Former Member
0 Kudos

Hi

Please check following prequisites-

1.HR mini-master record (infotypes 0001and 0002).

2.Assigned work centers to the internally processed activities.

3.Entered Formulas in the work center to determine capacity requirements.

4.Scheduled the activities to generate capacity requirements.

5.Assigned only one labor capacity to a work center. (that is catagory 002)

6."Determine Cap. Check" indicator is ticked in the network header.

Regards

Former Member
0 Kudos

Hi John,

Please try out the following link as it may help you :

http://help.sap.com/erp2005_ehp_03/helpdata/EN/4c/2279eb46e611d189470000e829fbbd/frameset.htm