on 11-11-2008 4:40 AM
hi,
in classic scenario, when we create a SC it is creating a PR in backend system.with reference to that PR i am creating a PO in backend system.but the same PO number(copy) has been replicated to EBP system.on what basis it is replicated.
is there any program that needs to be scheduled in backend system?
kindly calrify my doubt.
regards
subhash
Hi Shubash
In classic scenario, The PO will be created andavailable in R/3 not in SRM. The PO will not be available in EBP.
In ECS, The PO will be created in EBP and copy will be sent to r/3.
check it up.
Regards
Muthu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
dear Muthu,
i have created a SC in EBP where it created PR in backend and w.r.t PR i have created a PO.
now i need to do confirmation of SC in EBP.if i complete my confirmation in EBP material document will be created in backendsystem also.
My doubt is how we are able to do confirmation in EBP for that particular SC w.r.t what?
please calrify this
regards
subhash
check yr settings under
SRM IMG>Supplier Relationship Management>SRM Server>Cross-Application Basic Settings>Activate Extended Classic Scenario
&
if there is any implementation of
BBP_EXTLOCALPO_BADI
BR
Dinesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.