hi,

in classic scenario, when we create a SC it is creating a PR in backend system.with reference to that PR i am creating a PO in backend system.but the same PO number(copy) has been replicated to EBP system.on what basis it is replicated.

is there any program that needs to be scheduled in backend system?

kindly calrify my doubt.

regards

subhash

Accepted Solutions (1)

Accepted Solutions (1)

former_member183819
Active Contributor
0 Kudos

Hi Shubash

In classic scenario, The PO will be created andavailable in R/3 not in SRM. The PO will not be available in EBP.

In ECS, The PO will be created in EBP and copy will be sent to r/3.

check it up.

Regards

Muthu

Former Member
0 Kudos

dear Muthu,

i have created a SC in EBP where it created PR in backend and w.r.t PR i have created a PO.

now i need to do confirmation of SC in EBP.if i complete my confirmation in EBP material document will be created in backendsystem also.

My doubt is how we are able to do confirmation in EBP for that particular SC w.r.t what?

please calrify this

regards

subhash

former_member183819
Active Contributor
0 Kudos

Hi Subhash,

You can do confiramation against the PO created in the backend .

regards

Muthu

Former Member
0 Kudos

Dear Muthu,

On what basis the PO will be replicated in extended classic in backend system.do we need to execute any programs in EBP apart from CLEAN_REQREQ_UP AND BBP_GET_STATUS_2

REGARDS

SUBHASH

Answers (1)

Answers (1)

Former Member
0 Kudos

check yr settings under

SRM IMG>Supplier Relationship Management>SRM Server>Cross-Application Basic Settings>Activate Extended Classic Scenario

&

if there is any implementation of

BBP_EXTLOCALPO_BADI

BR

Dinesh