Enterprise structure for PS

Former Member
0 Kudos

Please help me understand the pre-reqs for PS implementation. As in what are the enterprise structure elements and pre-requisites for project implementation in PS.

Thanks,

A

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hello,

PS uses Enterprise Structure from other modules of SAP. From FICO -->Controlling area, Company Code, Plant, From SD module --> Sales organization, Division, Distribution channel are to be configured before PS is configured

All this is picked up in the Project from Project Profile which can also be changed during project creation.

Thanks

Anish

Former Member
0 Kudos

Hi,

SAP Project Systems supports comprehensive functions for planning, controlling & organizing all activities carried out during the course of a project. It helps you manage your project structures, dates, costs, and resources throughout the entire project lifecycle. Project Systems is management approach which enables users to compare and analyze various projects effectively with a clear and comprehensive integrated methodology in order to ensure an expeditious management decision making.

Project u2013 activities executed by different departments for a common objective/purpose and in which the total budget satisfies a standard amount for each objective/purpose.

At the highest level of SAP PS, projects are defined and then structured into an organizational form that maps to the specific project.

1. Work Breakdown Structure : The project is first broken down into work breakdown structures (WBS) which map to specific project deliverables.

2. Networks : Each WBS can then be broken down into networks of activities. A network can be thought of as a list of tasks organized into a process flow with specific timing.

3. Activities:Activities are the key tasks to be completed. These activities map to internal activities, external activities, cost activities and materials components.

4. Work Centers:Internal activities are assigned to work centers (resources) to be completed.

Regards

Tushar

Former Member
0 Kudos

thanks

Former Member
0 Kudos

PS uses organization elements (Enterprise Structure) from other modules. Controlling area, Company Code, Plant, Sales organization, Division, Distribution channel are to be configured before PS is configured