Hi All,

When iam assigning WBS elememnt with project ellement while saving system is giving following warnings

1.Costing data may not be up to date

2.Rollback: Account assignment must be reset

Costing data may not be up to date

Message no. DPR_FIN_GECCO044

Diagnosis

You made changes relevant to costing for data that has already been saved. However, the system could not update the costing (for example, errors occurred during costing or costing was locked). This message can still occur even if costing took place offline for the last data to be saved. If this is the case, the costing data is correct but the planned costs displayed in the dashboard may not be correct.

Procedure

Make a dummy change in the project and save again. It may be necessary to trigger the evaluation to update the planned costs in the dashboard.

Deepa

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

hi,

is this related to cprojects or PS?

thanks

amit

Former Member
0 Kudos

Hi Amit,

I am also facing the same problem what Deepa Khatri is facing.....and it is related to cProjects.

Any help provided is welcome....

Thanks and Regards,

Amit Gupta

Former Member
0 Kudos

hi amit,

have u assigned cost/revenue rates to project roles?

and replicated these rates to CO. ?

if not do this first, otherwise i send u accounts integration document with cprojects.

ur mail id?

thanks

amit