Hi,

while creating the Material Master it's prompting me to enter MRP controller and when I was look into this its becoming greayed out. Eiither I cant able to go further or enter the MRP controller So could some one guide me how to overcome this.

Is there any option that to deactive this field during the Material Master creation.

Please guide me.

Thanks

ANGKS

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hello,

While creating Material Master, if you had selected MRP tabs, then system will ask for MRP controller. Go to transaction OMD0 and define MRP controller.