on 11-09-2008 7:35 AM
Hi All,
I have configured a Direct Leg in the route & shipment type as outbound delivery. The shipment costs have been calculated & account assignment is calculated & assigned to the GL account & Cost center & the service entry sheet has been created & fully transfered to FI. The document flow in the delivery shows the shipment as fully calculated & Completed, but in the transportation tab of delivery the transportation status is 'B', & when Iam transfering the costs to the Billing document, the log says that as the copy control is configured as shipment costs "F" the delivery is not completed with relevant to transportation.
Can anyone suggest what else needs to be done to complete the billing.
Thanks In advance.
Regards
Aravind
answered
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Please check the copy control from Delivery to Biling.
Also check the pricing procedure attached to Delivery.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Aravind,
Please go to VL02N transaction enter the delivery number then go to the menu EDIT --> Click on Incompleteness now system will give the details about incompleteness proceed accordingly.
Make sure that you have done the PGI for that delivery before going to billing.
I hope this will help you,
Regards,
Murali.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Aravind,
Hope, the document may help you some extent:
http://help.sap.com/saphelp_47x200/helpdata/en/5f/e411bb044411d2bf5d0000e8a7386f/content.htm
Best Regards,
Amit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hello, friend.
please check IMG > Log Ex > Shipping > Basic Shpg Funcs > Pricing > Define pric proc for delivery. since your price source in copy controls is F, it is possible the system is looking for pricing data from delivery to billing.
please post again if this part has already been checked and done.
regards.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Jonathan,
The price source in the copy control of delivery to billing is "F" i.e. price from shipment costs. The shipment costs have been fully calculated & the status in the shipment cost document is "C". In the delivery the status of transportation planning is set as "B", which is partially processed.
The pricing as you have mentioned of delivery to billing for delivery pricing procedure is not maintained.
Thanks & Regards
Aravind