In the following scenario plz help.
in the job work tht client is doing. we r making a production order of a NON VALUATED DUMMY MATERIAL.
the raw material which the customer gave to us was lets say 100 kg.
after doing the job work i.e. after confirming the producion order the quantity made is 105 kg.
I have to give customer only 100 kg.
so rest 5 kg is in my stock.
client want to convert it into its valuated stock.
can u please help in mapping this scenario in SAP
hello, friend.
i believe this can be done with consideration to 'co-products'. this would involve MM and PP. as i am an expert in neither modules, please take my suggestions with a great of salt.
regards.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
One suggestion,
Do with tcodes, after you can do it with BAPI's
1. Do an entry of subproducts: mov 531 with tcode MB11
2. Do a transfer between materials (from a free good to a valuated good): mov 309 with tcode MB1B
I hope this help you,
Regards,
Eduardo
Edited by: Eduardo Hinojosa on Nov 7, 2008 5:50 PM
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.