Assignment Number is causing the billing to split. Is there any way to skip this checking?
I would like to combine different deliveries (with different assignment number) into 1 billing.
Thanks,
Soo
Dear Kah,
Please check following setting in
T. Code: VTFL
Select your Delivery--Billing combination and double-click to check Header-level settings. Check following entries within Fields:
Copying requirements 003 Header/dlv.-related
Determ.export data B
Assignment Number E
Reference number B
Also, check the Box: Copy item Number
Now, from left-hand tree, Click: Item (to maintain Item-level settings) and select your Item Category and Double-Clck.
Here, check entries for Fields:
Copying requirements 004 Deliv-related item
Data VBRK/VBRP 007 Inv.Split (Rec/Div)
Hope this may resolve the issue.
Best Regards,
Amit
Note: If all seems to be maintained as suggested above, and still Billing-Splts, remove the entries for Field: Allocation Number and Reference number and try.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.