on 11-06-2008 11:54 PM
Hi all,
We are working on SRM 5.0(SP12) and Extended classic scenario.
The problem is that after the PO ís ordered it gives the message " Error while reading PO in backend system Inform system administrator" .
When I check the PO number in R/3 it does not exist.
The number range is correct both in SRM and R/3 (external no. range is ticked).
In RZ20,i find the log:
The error ocurred by processing event SENT_AGAIN with GUID 490F3C0834351AC6E10000000AE48838 and object_id= 3000000307
The R/3 System Version is 4.6C.
Any help is highly appreciated.
Please cross-check all below settings:
1) IMG-> extended classic activation\
2) Number ranges for local PO in SRM and external number range for PO in R/3, must be same.
3) Make sure if you have any ECS_PO_OUT_BADI active ?, if yes then ask developer to debbug the transfer
4) Have you got the Location/Plants replicated from R/3
5) Check entries in table BBP_DOCUMENT_TAB and txn RZ20
6) Check out this Note: 508972
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
test yr po in question in FM BBP_PD_PO_TRANSFER_EXEC
& check the error message you are getting
if the error is not clear then you can debug this FM also
BR
Dinesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Please update here your no range configuration in both system for your local po.
Are you facing this problem for all po or only one PO?.
Did you do anything on SENT_AGAIN event.Note 1258634 - Certain events cannot be de-activated.
Are you sure still PO did not reach R/3 system.
Any error in SM58 ,sm12 for that particular user?
what is the latest status in BBP_PD for PO( follow on document created, transfer in error like that) or what is the status of follow on document in your SC.
regards
Muthu
Hi,
Thanks for the response.
This problem is hapeening for all PO's in the system.
The no range is smae in both the systems.In SPRO ,howevre we have not maintained the no range in SRM for R/3 system.
Here is the config details:
Supplier Relationship Management>SRM Server>Cross-Application Basic Settings>Number Ranges>SRM Server Number Ranges-->Define Number Range for Local Purchase Orders
EC 3000000000 3999999999 3000000320
Supplier Relationship Management>SRM Server>Cross-Application Basic Settings>Number Ranges>SRM Server Number Ranges-->Define Number Ranges per Backend System for Follow-on Documents
SAPE02_050 EC RS
Supplier Relationship Management>SRM Server>Cross-Application Basic Settings-->
Define Transaction Types
ECDP PO: Direct Material 03 02
ECPO Purchase Order EC
I have already gone thorugh note Note 1258634 - Certain events cannot be de-activated.
This note is however valid for SRM 6 and 7.
PO is not reaching R/3 system.
No error in sm58/sm12.
The status in BBP_PD for the PO is :
Stats:
Status Description Inact
HEADER I1009 Held X
HEADER I1015 Awaiting Approval X
HEADER I1021 Created
HEADER I1038 Complete
HEADER I1043 Ordered
HEADER I1080 In Transfer to Execution Syst. X
HEADER I1180 Document Completed
Awaiting your inputs.
Hi
What is the latest status of that PO in BBP_PD? Hope connections between srm and r/3 works fine via sm59.
regards
Muthu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.