on 11-06-2008 1:22 PM
Hi Friends,
I have created one sales order and when I am going thruGo to>item data-->schedule lines then confirmed quantity is showing zero(0).
I want that confirmed quantity should come equal to order quantity.
Regards
hi,
check the schedule line catagory setting, assign the availability check and requirement type
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
a
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi there,
Check if stock is there in the plant in MMBE. If not there post the stock in the plant. Item will not get confirmed only when the stock is not there.
Also in the customer master shipping data donot select anything in partial deliveries. This will make the system to confirm all the quantity of the items at one time rather than confirming partial deliveries.
Regards,
Sivanand
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi friends,
When I am trying with mov. type 561 or other and entering the material ,quantity,st. location and saving then getting the below error.
Any pointers.
G/L account 11500888 blocked for posting in company code 730
Message no. M7 161
Diagnosis
No postings can be made to a G/L account that is blocked.
Procedure
Determine whether another G/L account is suitable for the transaction.
Inform the individual or section responsible for G/L accounts in the relevant company code.
2.Also if I am trying with other matrl( having sufficient unrestricted stock available) then for that also quantities are not matching. why like this ?
Regards
Edited by: Amit Kumar on Nov 7, 2008 5:07 AM
Dear Amit,
I need some information from your side:
1. T. Code: VOV6
Select your schedule line category (Whats your Schedule Line Category? I assume as "CP") and check whether you have checked the boxes "Availabillity" and "Req/ Assembly"?
2. Check which checking group you have assigned in Material Master? Afterwards, check the setting in T. Code: OVZ2 & OVZ9
3. Apart from checking the stock in MMBE , check the ATP quantities in T. Code: CO09.
Best Regards,
Amit
Note:
Also, Plant, Shipping point and Route (for Availabiliy Check) have picked up in the order or not?
T code MB1C
movement type 561
Regards
raja
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Amit
In Make To Stock scenario, If stock is not available for a material and if you create a sale order for that material, system will show only zero quantity under the tab "Confirmed quantity".
On the other hand, if it is Make To Order scenario, as and when you create a sale order, that quantity will be confirmed immediately. Of course, you can generate delivery but cannot do PGI unless stock is made available.
thanks
G. Lakshmipathi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Check in t.Code MMBE for enough material stock. If enough stock is available, then the order quantity will be confirmed.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.