on 11-06-2008 1:23 PM
Hi all.
In t.code CN25, when the Degree of Processing is 100%, the COMPLETED indicator is automatically selected. I don´t want that this field be automatically selected, how can I do this?
Regards
This is standard process......if you are confirming 100% then it shld be completed.
Regards
Abhinay
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
This can be done.. Use t code OPST (confirmation parameters), in the Default parameter tab. remove the tick from "Final Confirmation" check box.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
the completed indicator means that there is no remaining work, so if you enter degree of processing as 100% it automatically sets the completed indicator as the system has been informed that there is no remaining work as 100% has been processed - this is as per standard SAP - as mentioned earlier by Abhinay