on 11-06-2008 9:30 AM
Hi ,
I want to know how we can implement PS module in Steel Industry where the scenario is like client has its own mines from where extract the ore and then this is treated into a sponge iron and finally processed to hot rolled coils.
If anyone who has the exposure of such kind of scenario or if anyone who can give me an idea , will be a great help to me.
Thanks,
Dhruv Kumar Malhotra
this would be covered by PP-PI
however if your plant was to be extended or modified or new plants to be built then PS could be used
also if you were managing a customer requirement for a steel order then you could trigger your production via PS
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
for this you can see sap help for details
generally the process will
create a project - your extension project
plan and budget - plan cost and materials for your project
get budget approved - can use IM for this
execute project - enter actual postings for materials, cost and also do scheduling, material purcahse orders, goods issues/ receipts etc
financial settlement - settle as required e.g. to AUC/ FXA
reporting will be across the project