I am Transferring BOM to the project CN33, while saving the tranasfer - instead of Reservation for WBS - PR's are getting generated for all the items though it is stock item.

in selection parameters i have selected Prelimininary Req.( to avoid requirement doubling), Multilevel ( BOM Explosion), project Stock 1

Please Do suggest

Venkatesh

Accepted Solutions (0)

Answers (3)

Answers (3)

kalpesh_agrawal
Participant
0 Kudos

hi Venketsh,

Since you have selecte preliminary reqts, system is genrateing PRs' although those are stock items. If you want to genreate resrevation for wbs only then remove prel.req. tick and transfer the BOM.

Regards,

Kalpesh

venkatesh_kulkarni1
Active Participant
0 Kudos

.

virendra_pal
Active Contributor
0 Kudos

check your configuration of procurement indicator OPS8 it must be set to reservation for WBS

venkatesh_kulkarni1
Active Participant
0 Kudos

Hi Virendra,

In OPS8 i am Having

PEV Planned independent reqmnts for WBS

PF PReq for WBS

PFS Third party requisition for WBS

PFV Prelim. req. for WBS

WE Reservation plant stock

Z01 Reservation for WBS Element

is there any way to set to Peservation For WBS

see

PEV is for Preliminary req. for MRP Item catagory L

PFV is for Preliminary req. for MRP Item catagory N.

Thanks

Venkatesh

Former Member
0 Kudos

Hi,

Please remove the tick from'' Preq for Network'' in OPS8 and then try.

Regards,

Amit

virendra_pal
Active Contributor
0 Kudos

also ensure that item category is L