I am Transferring BOM to the project CN33, while saving the tranasfer - instead of Reservation for WBS - PR's are getting generated for all the items though it is stock item.
in selection parameters i have selected Prelimininary Req.( to avoid requirement doubling), Multilevel ( BOM Explosion), project Stock 1
Please Do suggest
Venkatesh
hi Venketsh,
Since you have selecte preliminary reqts, system is genrateing PRs' although those are stock items. If you want to genreate resrevation for wbs only then remove prel.req. tick and transfer the BOM.
Regards,
Kalpesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
check your configuration of procurement indicator OPS8 it must be set to reservation for WBS
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Virendra,
In OPS8 i am Having
PEV Planned independent reqmnts for WBS
PF PReq for WBS
PFS Third party requisition for WBS
PFV Prelim. req. for WBS
WE Reservation plant stock
Z01 Reservation for WBS Element
is there any way to set to Peservation For WBS
see
PEV is for Preliminary req. for MRP Item catagory L
PFV is for Preliminary req. for MRP Item catagory N.
Thanks
Venkatesh