on 11-04-2008 3:53 PM
Hi guys,
Is there a way to run a multilevel heuristic (in /sapapo/sdp94) for product P1 in location L1 and its components only in location L1? I am asking because now when I run a multilevel heuristic it plans in all existing locations. That's not acceptable as we have one and the same product/material in different locations (countries) and multilevel heuristic changes the planning results everywhere.
Regards,
Alper
Please run Location Heuristic for that Product , you can pull toolbar for location heursitic by going into design mode in /SAPAPO/SDP94.
SAP Help.
o If you select Location (Heuristic), the system plans the specified
products in the specified locations. This allows you to select part
of the model to be planned, for example.
With both heuristic options, you can also specify that you want the
system to take into account all BOM components of the selected products
during planning. To do this, set the Take into account found components
in planning run indicator. The system then also plans the dependent
demand for the products. However, with the location heuristic, the
system only plans components that have been assigned to the specified
locations.
Manish
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Manish,
Ok, I can set the 'Take into account found components
in planning run' indicator in /SAPAPO/SNP01, but it will be used only if I run the heuristic in background mode. How can I set it to be taken into account when I press the Location (Heuristic) button in /SAPAPO/SDP94?
Regards,
Alper