I want to transfer the cost(activity cost) from one WBS element to another.
I have entered WBS, COST CENTER and ACTIVITY in time sheet(CAT2), and transferred to controlling thru tcode CAT7.
It is generating controlling document.
for example 5 hours entered in time sheet and it is converting to amount by taking activity price, now i want to transfer say 2 hours from WBS element to another.
I am using tcode KB65 is it right tcode to use for above requirement.
Please suggest.
Regards
KB65 is not the correct transaction
you should use KB21N to adjust the postings in your case