Hi Gurus,

In my report, i am supposed to pick the current budget field of the transaction CJ30.

For a WBS Element , i will pick Objnr from prps and use it in BPGE to pick WTGES.

But for a project definition it is not working..

i do not know from where i should pick if it is for a Project definition

Need ur help..

Thanks in advance

Deepak

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

You can not have budget for Project defination.If you wish to fetch project defination as an information it can be done with reference to WBS using table PROJ.

Regards

Answers (1)

Answers (1)

Former Member
0 Kudos

thanks