Hi Gurus,
In my report, i am supposed to pick the current budget field of the transaction CJ30.
For a WBS Element , i will pick Objnr from prps and use it in BPGE to pick WTGES.
But for a project definition it is not working..
i do not know from where i should pick if it is for a Project definition
Need ur help..
Thanks in advance
Deepak
Hi
You can not have budget for Project defination.If you wish to fetch project defination as an information it can be done with reference to WBS using table PROJ.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
thanks