Project summarization configuration

Former Member
0 Kudos

Dear Experts,

Please guide me on configuration for project summarization step by step. To my knowledge, this will allow us to report by WBS master data attributes e.g. business area

How do we go about configuring this? And, then how do we get a summarization report by a desired characteristic??

Please enlight me.

Regards,

Monica

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos
Former Member
0 Kudos

Thank you Hemant for helpful answer. I tried; and was able to follow the material suggested.

Another question about the same issue, can we use the summarization created in standard PS report? I tried by assigning a project view to a database profile, but when I ran the report, i don't see any difference.