on 11-04-2008 3:31 AM
Dear Experts,
Please guide me on configuration for project summarization step by step. To my knowledge, this will allow us to report by WBS master data attributes e.g. business area
How do we go about configuring this? And, then how do we get a summarization report by a desired characteristic??
Please enlight me.
Regards,
Monica
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thank you Hemant for helpful answer. I tried; and was able to follow the material suggested.
Another question about the same issue, can we use the summarization created in standard PS report? I tried by assigning a project view to a database profile, but when I ran the report, i don't see any difference.