on 11-03-2008 2:22 PM
Dear All,
In an investment project, I posted actuals to a WBS and ran Cj88, since the auc is assigned to the project due to the investment profile,the WBS got settled to the AUC and the settlement rule got created in the WBS with AUC(FXA) as receiver and settl type AUC.
Now what should be the next step to move the amount from AUC to fixed asset, i tried creating a settlement rule to the wbs with a fixed asset as receiver and ran Cj88 the system says nothing to settle.
Am i Missing something.
Your guidence is highly appreciated.
Regards
Hi Vinay,
Go to CJIC, enter WBSE, select all lines displayed or one by one and press ;settlement rule. Maintain the rule here.
go back to CJ88/CJ8G
If you choose 'Automatic Settlement' then your WBSe should be TECO. other wise choose 'partial capitalization' or 'full settlement' and run the settlement.
with regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
To do the settlement from AuC to fixed assets you could use tcode AIAB. Choose the line item of AuC amount to be settled and click "enter distribution rules" icon (Shift+F6) to maintain the settlement rule.
After the status of the line item goes into green then continue with "execute" icon to do the settlement to fixed asset.
Hope this helps.
Thanks.
Edited by: JSG on Nov 4, 2008 4:06 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
the wbs must be TECO to settle from AuC to FXA if settlement processing type is automatic in CJ88
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Create a second settlement rule with the fixed asset and with settlemet type full.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You can use the following transaction:
CJ88 Settle projects - post acquisition cost to general ledger
CJ8G Collective project settlement
In this case you have to make the settlement rule in your WBS
CJ70 Line item distribution
CJIC Line item distribution (same as CJ70)
In these transaction you fill in the settlement rule, save and click on the button Settlement and you jump to CJ88.
In this screen you see al the postings and make a different settlement rule by posted line (invoice)