on 11-03-2008 10:30 AM
Hi All...
I Created a project with two WBS element.
While Closing the project, i closed all the Activities in the network, but when i try to close the wbs element, i got these error message
WBS B/XXXX/XX : WiP in Financial Accounting is still to be cleared/settled
Balance of WBS B/XXXX/XX is not zero
There is still WIP for WBS B/XXXX/XX
I run cj88, no cost is captured or posted
Already i have posted.... can any one guide me, how to find out, where i left the settlement...
Rgds
Pithan
Hi
You can not close the project if there are committments/actuals on it. Check CJI3 for actuals and committments with CJI5, orelse S_ALR_87013533.
Clear actual cost/revenue and commitments first.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
94 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.