Budget transfer from PS-WBS Elements to Cost Centers

Former Member
0 Kudos

Hi All,

I would like to do budgeting for a company level ,(i.e Cost Center Level)

I have PS Module Budgeting also.

The question is :

1.Cost Center Budgeting is different (KPZ2) & PS WBS Element Budgeting is different (CJ30).But Cost Center budget should include Project (WBS) Budget as per the normal business scenario.

So,while doing Cost Center Budgeting ,i need to include Project budgets & enter the value.(its a manual entry approach)

Suppose am not including the project budget in cost center budgeting(am doing Project budgeting seperately) ,then is there any T-code which will roll up Project Budgets to Cost Center?

Thanks

Suresh

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Use Investment Positions (IM) instead of Cost Centres as you refer and every thing is possible as you wanted.

PS budgets and Cost Centres budgets are no where linked.

Regards

Sreenivas