System not calculating the Project Work In Process

former_member774432
Participant
0 Kudos

Hi Experts..,

System did not capturing my plant cost & revenue, which I planned against WBS Element while calculating the work in process. In place of plan cost system is showing plan cost same as actual cost

*Example : -

Plan Cost : 120000

Plant Revenue : 200000

For 1st Period

Actual Cost : 20000

Actual Revenue : Nil

In Work in process Calculation (T. Code :KKA2) system result

Actual cost : 20000

Plan cost : 20000

Plan Revenue : 0.00

WIP : 0.00

System not capitalizing the cost as well as cost capturing the real plan cost & revenue in WIP result. I tested with Result Analysis Methods:-

01 Revenue-Based Method - With Profit Realization

02 Revenue-Based Method - Without Profit Realization if Actual Revenue < Plan Costs

03 Cost-Based POC Method

06 POC Method on Basis of Revenue Planned by Period

WIP result is same no change in all above methods. Please help me

Check my configuration also in below link

http://www.usaupload.net/d/ob519mw8qni

Please do needful

Thanks

PRBR

Edited by: Bhagiradha Pinnamareddy on Nov 3, 2008 2:33 PM

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi ,

To Calculate WIP, U need to run Result analysis. For that u need to maintain Result Analysis Key in the project. Refer below steps for RA Config.

Configuration steps for RA.

Result Analysis.

1. Maintain RA Key (Tcode: OKG1)

2. Maintain RA Version (Tcode: OKG2)

3. Define Valuation method for RA (Tcode : OKG3)

4. Define Line ID's

5. Define Assignment of RA (Tcode :OKG5)

6. Define Update for RA (Tcode: OKG4)

7 Define Posting rules for settlement to accounting (Tcode: OKG8)

8. Maintain the RA Key in Tcode: OPSA Controlling tab, if the Default RA key is to be maintained while creation of the project.

check the same and revert

regrds

pushpa

former_member774432
Participant
0 Kudos

Dear Pushpa,

Thanking you for ur replay. plz check my configuration steps in above like then give me suggestion for any modification in my configuration

Thanking you

Bhagiradha

Answers (1)

Answers (1)

former_member774432
Participant
0 Kudos

CJR2 is must for WIP Calc.