Dear all,

i've created a project with network

i created a cost center

i created an activity type and assigned it to the cost center

i planned cost and activity inputs & activity output/prices for the activity type

i created a work center and assigned it to the cost center

i assigned an internal activity to a work center

i scheduled the project

BUT tell now when i run the report S_ALR_87013542 there is no values for planned costs for this activity on allocation cost element defined for the activity type

WHY ???!!!

N.B: i'm sure of the correctness of all assignments

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Pl see under network header (control tab)->Costing ->Planned cost calc whether planned cost calculation is permitted.

Murali

Former Member
0 Kudos

yes sir,

it's "Determine plan costs"

Former Member
0 Kudos

Hi

check in the control key of the activity (OPSU) if "cost" indicator is ticked.

Regards

Former Member
0 Kudos

what do you mean by activity (OPSU) ??

and how can i check this ??

Former Member
0 Kudos

OPSU is the transaction code in which you will be able to see the control key parameters.

Former Member
0 Kudos

yes it's checked