on 10-30-2008 11:38 AM
Dear all,
i've created a project with network
i created a cost center
i created an activity type and assigned it to the cost center
i planned cost and activity inputs & activity output/prices for the activity type
i created a work center and assigned it to the cost center
i assigned an internal activity to a work center
i scheduled the project
BUT tell now when i run the report S_ALR_87013542 there is no values for planned costs for this activity on allocation cost element defined for the activity type
WHY ???!!!
N.B: i'm sure of the correctness of all assignments
Hi,
Pl see under network header (control tab)->Costing ->Planned cost calc whether planned cost calculation is permitted.
Murali
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.