cancel
Showing results for 
Search instead for 
Did you mean: 

how to change plant in sales order???

Former Member
0 Kudos

I have made a sales order which created a purchase requisition. A purchase order has been made with reference to the purchase requisition.

No goods reciept has been made yet.

I want to change the plant and the storage location in the Purchase order, so to be able to recieve the goods in a different plant. I tried doing this from ME22n but I get the message that the sales order has been made with a different plant. If I try to change the plant in the sales order I can not. the field is not possible to be changed.

What should I do?

Thank you in advance

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Dear Theodorous,

1)Please check the Material has been extended to the second plant.

2) Assign the second Plant to Sales Org and Dist Channel

If you have any concern revert back the same

Regards

Amjath

Former Member
0 Kudos

Hi there,

Once the subsequent docs are created for the SO, you cannot change the plant.

Try cancelling the PO & PR & then change the plant in VA02.

Make sure that you change the plant & other critical details before creating the follow on docs like delivery or PO.

Regards,

Sivanand