on 10-30-2008 5:45 AM
Hi Friends,
I am doing easy cost planning---> execution services for Internal activity allocation but when I am posting the document getting the below error.
How can I overcome this.Pointers will be rewarded.
Business process 300900 is not yet planned in version 0/2008.
Message no. BK505
Diagnosis
You did not carry out planning for business process 300900 in fiscal
year 2008, version 0.
Because process 300900 also has no active actual price indicator, you
cannot carry our actual allocation.
Procedure
In order to allocate to the business process in actual:
o Carry out activity planning for the process
o Alternatively, set the actual indicator for the process so that the
R/3 System carries out revaluation in actual
Carry out planning and maintenance of the price indicator in the
Activity-Based Costing component.
Regards
Hi Amit,
Please check if you have defined the Cost Center/ Work Center and Activity Type relation in KP26. This is required for posting of costs.
Hope this helps.
Thanks
Venu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
got
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Amit,
1. Check the master data settings of process 300900 in CP02. In the "Allocation" tab. all the necessory settings are maintained such as process diriver and defalut values like cost element, actvity allocation (should be "1" i.e. manual entry in your case)
2. Maintain the planning data for this business process through CP26 for year 2008.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.