on 10-30-2008 5:43 AM
Hi All,
I wanted to know how many CO Plan Versions are recommanded for an Project, Is it that we can create about 30 or 40 versions. Does this has any impact on the system. My client wants to use the 40 CO Versions. Is it good idea?? Please suggest
Thanks,
Steve
hi,
i think 30 - 40 versions is too much..
it would be too tedious to maintain and to analyze in reporting..
regarding system performance, i think its alright..
i just dont see the need to create so many versions, maybe max ideal would be around 15 (for each period plus other additional versions)..
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
There should not be any problem creating 40 version but actual will onlly be posted at 0 version, Just take care of RA tick against each version.
Regards
Gaurav
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.