I've a requirement where I need to move a WBS within the hierarchy. But, I want to do it after budgeting. When I do, Edit -> Object -> Move, SAP is giving std. error message CJ418 - WBS can no longer be shifted.

I understand SAPs intent because of budget availability and moving from different levels. But, I have only level-2 wbs elements and no other levels. So, I've no influence in availability. Can anyone let me know if this can be achived?

Thanks for the help

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

Not possible to do it with budgeted WBS. You need to remove the budget and then run OPSX to revoke the "BUDG" status from WBS, then you can shuffle the WBS.

Regards