while doing packing i am getting a message
1. in the loop 1 no packing proposal data could be determined.
2. no packing instructions could be found for material.
How to resolve this issue. and how to maintain handling units.
Thanks
Chetan
Hi Chetan, you can manually perform packing without packing instruction. if you really need it, you should check whether the packing instruction is maintained correctly, and activate it.
For handling units, first, create master data for packaging material as well as master data for packed material. Then, maintain the allowed packaging material/type in the master data for the packed material.