on 10-29-2008 8:05 AM
Hi All,
as you know route would be determined by the parameters cntry of dep,cntry of dest,shp cond from sales doc(sales order), transporatation grp from material.
is it possible to change the way how system determines Route?
i would like to take the shipping conditions from Ship to party in determining route(rather than from sales order).
how should i proceed??
please advise,
Whether it can be restricted at company code level?
pls let me know how i should proceed
Thanks & Regards
Balaji
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Dominik,
if i have different "Ship to" for each line item in sales order, whether this logic is going to work?
pls suggest
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You can change the logic in u-exit MV45AFZZ -> form userexit_move_field_to_vbak.
There you can read VSBED value from ship-to-party partner.
In fact this is a common bug that I experience in many projects.. not sure why SAP does not support this in standard..
Regards,
Dominik Modrzejewski
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.