Hi,
I have created an inquiry and project in the system after that in change inquiry i have assigned DIP Profile and WBS (Project Definition) to the Inquiry and after all of these I have done the cost planning for the project in CJ40 and now I am trying to process Project Quotation by DP81. giving the Project Definiton and on clicking Sales Price basis I am getting an error message "No Expenditure Item found"
Can any one help me for the same....? As per my view I have done all these things correctly.
Please suggest me if you have any idea what is missing by me in the system.?
Thanks and Regards,
Krishna Singh.
Dear,
You should procure material via project and make consumption with that paticular WBSE .By doing this you will able to create Qutation as the Plane and actual cost will assign to WBSE as needed in DIP profile.
Regards.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
system is looking for actual costs
your DIP profile for quotation should use planned cost and not actual cost
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
firstly your DIP profile must be correct i.e. should have planned cost for quotation
then you must create a WBS with planning - can use CJR2 or CJ40
in the inquiry link the WBS to the inquiry line item
now you should get the quote value
as you have error no exp item found - the system is looking for actual costs
You need to check you DIP profile - use transactions ODP1 and verify if the plan cost is applicable for quotation