on 10-26-2008 11:09 AM
hello,
while using scheduling agreement with delivery schedule, deliveries split according to unloading point. Is there a way to combine two deliveries that have different unloading points?
Dear SD,
First try to check with, Order requirement - 102 (atHeader) in to T. Code: VTLA, for your Sales Order-to- Delivery combination.
If it doesn't serve the purpose,
I think, you need to write a routine (Include Program: RV50B901) in to T. Code: VOFM, and
attach the routine in to Field: Order requirements, in to Sales Order-to- Delivery Copy Control settings (T. Code: VTLA; Item --> Item Cat.)
Best Regards,
Amit,
Note: Screen Field for Unloading Point: KUWEV-ABLAD