on 10-26-2008 11:43 AM
Hello Friends,
I'm new in SAP. I want to know what happens if I close a day in the factory calendar ? Would it be possible
to post goods issues or goods receipt ?
Is there different calendars possible ? receipts calendar ? customer calendar ?
Thanks a lot.
Romeo
Hi
The Shipping Point also will have a calendar assigned to it. If it is a working day as per the calendar assigned to the shipping point, then the deliveries can be processed and hence Goods Issue or Goods Receipt can be done.
Thanks,
Ravi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
There is no different posting for goods receipt and goods issue and so on. The posting period is GL Account posting which allow the GL Account posting so as to reflect that in P&L and Balance sheet of the company code, so as to give a real time reporting from SAP system.You cannot do posting on the dates for which period is closed. you need to change goods receipt and goods Issue date manually.You can check the same through transaction code MMPV, provided you have authorization of it.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.