In material master we have following situation, during procurement of row materials we have defined moving average price, same row material is after used in production and affects calculation of costing price which is calculated at the end of period, mothly basis. Now, we need first price on receiving plant correct but if stock on plant is negative than amount of price goes to cost account and is treated like standard and no more like moving average price and it also affects all receiving plants and their valuation.
So, my question is, is any other option, method or any suggestion how to keep negative stock but to have realistic moving average price?
Kind regards,
Anchi
11-04-2008 9:40 AM
Hi Anchi,
i hope you to Pay attention to the plant in which you want to change the moving average price and the valuation type (if any) that is used for this material and do chk for MARD Table.
Please check wheather neg stock is allowed allowed for that particular material in material master in Plant data/Store2 view.
Suggestion: 1. If in case if you want to change the MAP you can use T Code ; MR21
Path--> Logistic / material management / valuation / Valuation / Price determination / Change price .
Enter, the material, plant and valuation type and change it accordingly. New Price for (MAP)
Suggestion: 2 Go to OMS2 under Valuation tab,change the Price control for the particular material type, as STD Price and acct car ref. but make sure that your earlier customising setting remain same.
Thanks
Satish
11-04-2008 9:40 AM
Hi Anchi,
i hope you to Pay attention to the plant in which you want to change the moving average price and the valuation type (if any) that is used for this material and do chk for MARD Table.
Please check wheather neg stock is allowed allowed for that particular material in material master in Plant data/Store2 view.
Suggestion: 1. If in case if you want to change the MAP you can use T Code ; MR21
Path--> Logistic / material management / valuation / Valuation / Price determination / Change price .
Enter, the material, plant and valuation type and change it accordingly. New Price for (MAP)
Suggestion: 2 Go to OMS2 under Valuation tab,change the Price control for the particular material type, as STD Price and acct car ref. but make sure that your earlier customising setting remain same.
Thanks
Satish
11-04-2008 10:09 PM
Hi Sadish,
No, problem is of another nature, problem is that when material for a certain plant is with negative stock
stock = 0 and material V price = 1,
PO for 10 pc * 2 u20AC = 200,
GR = stock account 100
GR/IR 200
price difference = 100
but during GI system is issuing at material price = 1. And during stock tranfer from plant to plant it is with price 1 not 2. During moving average price and negative stock, moving average price is treated as standard price not moving. Until negative stock is covered system is calculating material like with standard price and I want to know what is possible solution for negative stock to have on all other plants and cost center corect curent price.
thanks
11-06-2008 9:35 AM
hi anchi,
if possible can you try with off set entry for the price difference of 100 usd. so as to trade off the account. so the materials which is having negative stock in some of the plants and more over, the system is considering the std price instead of MAP.
I dont the extact setting which is done..but you can try this option.
BT
Satish .
11-08-2008 10:58 PM
Hi,
Yes, I also though of it but is not a solution because I don't have realistic price because my documents for row materials are late. What I would like to know what other coleques did in this case. Maybe, some program to adjust the price change at the end of period and to recalculate expenses or something else? There must be something that can be done in this case, I don't think it is a new thing. I think that every company or industry that has production is dealing with the same problem, they can not stop production because documents for GR are late?
Thanks,
Ana
11-12-2008 7:20 AM
Hi Anchi,
This problem occurs many times. In this case we need to upload a stock with respect to open order. price will get updated.
Thanks