Hi ps masters,

If the Project Status is Closed then, what is the things we have to do.

Is it possible to capture the cost.

thanqu

raj

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Raj,

When the status is TECO it allows you to post or transfer actual costs but does not allow additional commitments.

When the status is CLSD it does not allow to post or transfer actual costs and additional commitments.

If you want to Post costs you can revert the status.

Rgds,

Nitin

Former Member
0 Kudos

Hi Nitin Ghadge,

thanqu for ur quick replay, but ur mentioned ur answer, it allow additional committment, what r the additional commitment.

thanqu

raj

Former Member
0 Kudos

Additonal commitments means that,

After setting status TECO you cannot create Purchase Requisitions and Purchase Orders.

Thanks

Answers (3)

Answers (3)

Former Member
0 Kudos

closed

ansar_shaikh2
Contributor
0 Kudos

If you change the status of your project to TECO, the status will remove any Reservations & allow commitments to be finalised.

In TECO status no more commitments.

CREATED status - canot post costs.

RELEASED status - Can post costs.

TECO - No more commitment.

CLOSED status - COMPLETED

HOPe this will help you to understand.

REGARDS.

ANSAR

Former Member
0 Kudos

In the subject u said TECO and where in the question u mentioned "Project is closed".

TECO and Closed is not same.

check out this link...

http://help.sap.com/saphelp_47x200/helpdata/en/a9/8a853488601e33e10000009b38f83b/frameset.htm

U can not post cost once project is closed. U have to reverse it to post the cost.

Venkat