on 10-24-2008 7:53 AM
Dear Gurus,
I have 2 products-
A is made out of B, i.e. B is child component of A. when i run optimizer, availability date is shown as 2nd of the month. this product starts on the date 1st and available on 2nd.
its child component also starts on 1st and ends on 2nd which is not possible. it has to be present before parent component's production starts.
kindly let me know the reasons for this abnormal behavior
bucket offset in pds and optimizer profile for both item is 0 and 1 respectivly and optimizer is running on monthly bucket.
Regards,
Nitesh.
Dear Nitesh,
1 If you are running in monthly bucket how do you get receipt date as 2nd?
2 Have you maintained GR processing time in child product by chance?
Nitin Thatte
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.