I want to CIF the Production version from ECC.In ECC BOM I am having 10 child components and I want to be only 4 child components to be CIFED from ECC of that production version.

regards

guru

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

Only 4 materials (components) should be in active integation model.

regards,

Alexander

nitin_thatte
Contributor
0 Kudos

Hi

You have to keep only those components as MRP type X0 which you want to take to APO. After yoy CIF materials and work centres you can CIF PPMs to APO without any problem. The PPM will not carry those components which are not X0. While CIFing system will warn you "BOM item not APO rekevent" which you can ignore.

Regards

Nitin Thatte